U. S. Army Corps of Engineers
                              Jacksonville District
 
                        Water Conservation Area #2 Report
 
Data Ending 2400 hours   24 FEB 2017
 
Note: Headwater, tailwater, and stage values below are instantaneous values
      unless otherwise specified.
 
             Headwater Tailwater            --------- Gate Positions ----------
             Elevation Elevation  Discharge  #1    #2    #3    #4    #5    #6
             (ft-msl)  (ft-msl)     (cfs)   (ft)  (ft)  (ft)  (ft)  (ft)  (ft)
 
Water Conservation Area #2A
  Site 2-17:   11.77
  Site 2-19:   11.44
  S7 Pumps:    10.35     11.32        0        0     0     0              (cfs)
  S7 Gates:                           0     0.00
  S11C:        11.31      9.60        0     0.00  0.00  0.00  0.00
  S11B:        11.32      9.54      100     0.50  0.00  0.00  0.00
  S11A:        11.33      9.47        0     0.00  0.00  0.00  0.00
  Total S11 Discharge:              100
  S144:         -NR-      -NR-               0.00
  S145:         -NR-      -NR-               0.00
  S146:         -NR-      -NR-               0.00
  S38:         11.35      7.63       88      0.40  0.40
  S38C:         -NR-      -NR-
 
Water Conservation Area #2B
  Site 99:      9.98
  S124:         4.98      4.48
  S34:          -NR-      -NR-       19      -NR-  -NR-
 
 
Daily Precipitation Totals        1-Day       3-Day       7-Day
                                 (inches)    (inches)    (inches)
  Site 2-17: (Bad Gage)            -NR-         0.00        0.00
  Site 2-19:                       0.00         0.00        0.00
  S7 Pump Station:                 -NR-         0.00        0.00
  S11A: (Bad Gage)                 -NR-         0.00        0.00
  -----------------------------------------------------------------
        WCA-2A Average (Gages)     0.00         0.00        0.00
        (Site 2-17 and S11A not included)
  -----------------------------------------------------------------
  WCA2A Nexrad Basin Avg           -NR-         0.00        0.00
  WCA2B Nexrad Basin Avg           -NR-         0.00        0.00
  -----------------------------------------------------------------
 
 
WCA-2A Area Regulation                     Elevation   Regulation  Departure
                                           (ft-NGVD)   (ft-NGVD)     (feet)
  Site 2-17                                   11.77       11.00       0.77
  Site S11B Headwater                         11.32       11.00       0.32
  Floor (Site 17)                             11.77       10.50       1.27
  Floor (S11BHW)                              11.32       10.50       0.82
 
 ------------------------------------------------------------------------------
 *     DATE     ! USE GAGE !                   CONDITIONS                     *
 * 1JAN - 31JAN !   2-17   !  If 2-17 stage recedes to 11.5 ft NGVD, switch   *
 *              !          !  to S-11B headwater gage.                        *
 * 1FEB - 30JUN !   S-11B  !                       ALL                        *
 * 1JUL - 31DEC !   2-17   !                       ALL                        *
 ------------------------------------------------------------------------------
 
                                           Site17   Diff      S11BHW   Diff
WCA-2A Elevations      24 FEB 2017         11.77              11.32
   24FEB17  -1 Day  =  23 FEB 2017 @ 2400  11.78     0.01     11.33     0.01
   24FEB17  -2 Days =  22 FEB 2017 @ 2400  11.79     0.02     11.36     0.04
   24FEB17  -3 Days =  21 FEB 2017 @ 2400  11.72    -0.05     11.30    -0.02
   24FEB17  -4 Days =  20 FEB 2017 @ 2400  11.71    -0.06     11.32     0.00
   24FEB17  -5 Days =  19 FEB 2017 @ 2400  11.72    -0.05     11.36     0.04
   24FEB17  -6 Days =  18 FEB 2017 @ 2400  11.73    -0.04     11.39     0.07
   24FEB17  -7 Days =  17 FEB 2017 @ 2400  11.75    -0.02     11.42     0.10
   24FEB17 -30 Days =  25 JAN 2017 @ 2400  11.96     0.19     11.85     0.53
 
 
Report Generated 25 FEB 2017 @ 21:38
** Preliminary Data - Subject to Revision **