sitrep
                 Situation Report of Hydrometeorologic Conditions
                       Jacksonville District (CESAJ-EN-WW)
                                   31 AUG 2026
 
 
Data Ending 2400 hours 30 AUG 2026
********************************************************************************
Kissimmee Basin Lake Regulation            Elevation   Regulation  Departure
                                           (ft-NGVD)   (ft-NGVD)     (feet)
  Hart & Mary Jane                            60.06        -NR-       -NR-
  East Tohopekaliga                           56.39       56.50      -0.11
  Tohopekaliga                                53.75       53.50       0.25
 
  Myrtle, Preston, Joel                       60.26       61.00      -0.74
  Trout, Coon, Center, Lizzie & Alligator     62.57       63.20      -0.63
  Gentry          Lake Gage = 60.63     S63 = 60.63       61.00      -0.37
 
  Cypress                                     49.20       51.50      -2.30
  Hatchineha                                  48.90       51.50      -2.60
  Kissimmee                                   48.91       51.50      -2.59
  Istokpoga                                    -NR-       38.48       -NR-
********************************************************************************
                  Okeechobee Lake Regulation
 
                                       Elev        Last Year
                                     (ft-NGVD)     (ft-NGVD)
Avg Daily Lake Okeechobee Elev         10.90          12.53
 Currently in Water Shortage Management Zone
              Regulation Schedule for 30 AUG 2026
    _________________________________________________________
    LOSOM24 Regulation ZoneA=        16.94
    LOSOM24 Regulation ZoneBC=       16.54
    LOSOM24 Regulation ZoneD=        12.36
    _________________________________________________________
 
Current volume of water in the Lake is  2,333,000 ac-ft.
 
Lake Okeechobee elevation is -3.29 feet below normal for this time of year,
based on todays historical lake average of 14.19 ft-NGVD for the period 1965-07.
 
Herbert Hoover Dike Emergency Action Plan
  Current Monitoring Plan Condition Level - NORMAL
  Monitoring Plan Condition Levels - see EAP page A-2 for more details
    Normal Operations - Lake level below 15.5'
               Lake Level       Inspection Interval, Notes
 
    Level 1 - 15.5 to 16.49      7 to 30 day, varies by reach
    Level 2 - 16.5 to 17.49      1 to  7 day inspections by SFOO, monthly
                                           by CESAJ-EN and OD staff
    Level 3 - > 17.5             daily, SFOO, CESAJ-EN and OD staff
********************************************************************************
WCA-1 Area Regulation                      Elevation   Regulation  Departure
                                           (ft-NGVD)   (ft-NGVD)     (feet)
  Site 1-8C                                   16.05       16.95      -0.90
  Average of Sites 1-7, 1-9, 1-8T             15.82       16.95      -1.13
 
  Regulation Zone Elevations              A2= 16.95   B= 15.93   C= 14.00
 
Storage at the current elevation is    143,780 ac-ft.
********************************************************************************
WCA-2A Area Regulation                     Elevation   Regulation  Departure
                                           (ft-NGVD)   (ft-NGVD)     (feet)
  Site 2-17                                   12.01       12.33      -0.32
  Site S11B Headwater                         12.05       12.33      -0.28
 
Storage at the current elevation for Site2-17 is    103,900 ac-ft.
Storage at the current elevation for S11B HW is     -NR-    ac-ft.
********************************************************************************
WCA-3A Area Regulation                     Elevation   Regulation  Departure
                                           (ft-NGVD)   (ft-NGVD)     (feet)
  Average of Sites 63, 64, 65                  8.84        -NR-       -NR-
  Site 62 - Deer Gage                         11.17       11.99      -0.82
  S-333 Headwater                              7.65
  Regulation Zone Elevations   B= 10.09    C=  -NR-    D=  -NR-   E=  -NR-
 
Storage at the current elevation is    304,000 ac-ft.
 
Site 71 elevation in WCA-3B is  7.02 .
********************************************************************************
Portugues and Bucana Rivers, Puerto Rico   Elevation   Regulation  Departure
                                           (ft-NGVD)   (ft-NGVD)     (feet)
  Cerrillos                                    -NR-      573.00       -NR-
********************************************************************************
 
Report Generated 31AUG2026 @ 09:15  ** Preliminary Data - Subject to Revision **